San Jose Boulevard (SR 13) Signals Improvements

Overview

The project includes new mast-arms and signals at San Jose Boulevard and Julington Creek Road, Westberry Road, Marbon Road, Orange Picker Road, Loretto Road, Ricky Drive and Mandarin Road. Other items of construction include pedestrian signals, highway striping, crosswalk striping, highway signage and concrete sidewalk.

Traffic will be maintained in accordance with FDOT design standards throughout the project. Drivers can expect periodic single lane closures during off-peak driving hours. Lane closures may occur from 8 p.m. to 6 a.m. seven days a week.

Florida Safety Contractors is expected to complete this $2.6 million improvement project in summer 2020, weather and unforeseen circumstances permitting.

The Florida Department of Transportation urges motorists to always follow the speed limit and stay within the limits of orange cones and barrels while traveling through construction zones.

Traffic Impacts

No alerts at this time.

Project Photos

No photos at this time.

Project Documents

No documents at this time.
No Events at this time.

Project Details

Project Start:June 2019
Expected Completion:Summer 2020
Cost:$2.6 million
Project #:432396-1
RoadsState Road 13
CountiesDuval
CitiesJacksonville

Contact

Daryl Goss
386-984-5392

San Jose Boulevard (SR 13) Signals Improvements

Overview

The project includes new mast-arms and signals at San Jose Boulevard and Julington Creek Road, Westberry Road, Marbon Road, Orange Picker Road, Loretto Road, Ricky Drive and Mandarin Road. Other items of construction include pedestrian signals, highway striping, crosswalk striping, highway signage and concrete sidewalk.

Traffic will be maintained in accordance with FDOT design standards throughout the project. Drivers can expect periodic single lane closures during off-peak driving hours. Lane closures may occur from 8 p.m. to 6 a.m. seven days a week.

Florida Safety Contractors is expected to complete this $2.6 million improvement project in summer 2020, weather and unforeseen circumstances permitting.

The Florida Department of Transportation urges motorists to always follow the speed limit and stay within the limits of orange cones and barrels while traveling through construction zones.

Project Details

Project Start:June 2019
Expected Completion:Summer 2020
Cost:$2.6 million
Project #:432396-1
RoadsState Road 13
CountiesDuval
CitiesJacksonville

Contact

Daryl Goss
386-984-5392
 
Link to FDOT's Facebook page (opens new browser window) Link to FDOT's Twitter page (opens new browser window) Link to FDOT's YouTube page (opens new browser window) Link to FDOT's Wordpress page (opens new browser window) Link to FDOT's Multimedia page (opens new browser window) Link to FDOT's RSS page (opens new browser window)