Florida Department of TRANSPORTATION

State Road 20 drainage improvement project

Overview

The Florida Department of Transportation (FDOT) is improving drainage along State Road 20 from Osceola Street to U.S. 17 (Reid Street). This area holds large amounts of water during storms due to the size of the current drainage pipes. Installing new drainage pipes along State Road 20 will allow water to move more efficiently from U.S. 17 to the St. Johns River.

The five-phase construction project includes, removing the top layer of asphalt and replacing it, installing new drainage pipes under the roadway, new storm drain construction, base work, curb and gutter improvements, sidewall and driveway construction, utility work, landscaping and other incidental construction items.

Periodic lane closures and road closures will be necessary throughout construction. Sidewalk closures may occur during the project; however, signage for pedestrian detours will be in place. Trucking traffic should utilize the existing truck route for State Road 20 and vehicles should adhere to the guided detours installed.

Throughout each phase of this project, a portion of State Road 20 will be closed to all vehicle traffic to safely complete the work. The road closures planned for each construction phase are listed and color coded on the provided map (figure 1). Each phase of work is expected to take between four to six weeks, weather and special circumstances permitting. The additional map provided (figure 2) displays the current detour in place for motorists.

Halifax Paving Inc. was selected to complete this project.

 

Traffic Impacts

State Road 20 traffic impacts
June 15-21, 2019

Full road closure from Laurel Street to Carr Street until August 2019 for drainage work.

Full road closure from Laurel Street to Carr Street until summer 2019 for drainage work.

Project Photos

No photos at this time.

Project Documents

No documents at this time.
No Events at this time.

Project Details

Project Start:Fall 2018
Expected Completion:Fall 2019
Cost:$2 million
Project #:428797-1
RoadsState Road 20, U.S. 17
CountiesPutnam
CitiesPalatka

Contact

Bianca Speights
904-360-5471

State Road 20 drainage improvement project

Overview

The Florida Department of Transportation (FDOT) is improving drainage along State Road 20 from Osceola Street to U.S. 17 (Reid Street). This area holds large amounts of water during storms due to the size of the current drainage pipes. Installing new drainage pipes along State Road 20 will allow water to move more efficiently from U.S. 17 to the St. Johns River.

The five-phase construction project includes, removing the top layer of asphalt and replacing it, installing new drainage pipes under the roadway, new storm drain construction, base work, curb and gutter improvements, sidewall and driveway construction, utility work, landscaping and other incidental construction items.

Periodic lane closures and road closures will be necessary throughout construction. Sidewalk closures may occur during the project; however, signage for pedestrian detours will be in place. Trucking traffic should utilize the existing truck route for State Road 20 and vehicles should adhere to the guided detours installed.

Throughout each phase of this project, a portion of State Road 20 will be closed to all vehicle traffic to safely complete the work. The road closures planned for each construction phase are listed and color coded on the provided map (figure 1). Each phase of work is expected to take between four to six weeks, weather and special circumstances permitting. The additional map provided (figure 2) displays the current detour in place for motorists.

Halifax Paving Inc. was selected to complete this project.

 

Project Details

Project Start:Fall 2018
Expected Completion:Fall 2019
Cost:$2 million
Project #:428797-1
RoadsState Road 20, U.S. 17
CountiesPutnam
CitiesPalatka

Contact

Bianca Speights
904-360-5471

Traffic Impacts

State Road 20 traffic impacts
June 15-21, 2019

Full road closure from Laurel Street to Carr Street until August 2019 for drainage work.

Full road closure from Laurel Street to Carr Street until summer 2019 for drainage work.

 
Link to FDOT's Facebook page (opens new browser window) Link to FDOT's Twitter page (opens new browser window) Link to FDOT's YouTube page (opens new browser window) Link to FDOT's Wordpress page (opens new browser window) Link to FDOT's Multimedia page (opens new browser window) Link to FDOT's RSS page (opens new browser window)

Florida Department of Transportation

Consistent, Predictable, Repeatable