Interstate 95 ITS Freeway Management Project

Overview

This is a 17-mile ITS (Intelligent Technology System) Freeway Management project along Interstate 95 from Airport Road in Duval County to the Florida-Georgia state line in Nassau County that incorporates a portion of A1A/State Road 200 just east and west of Interstate 95.

The project began in November 2017 with completion anticipated in spring 2019, depending on weather and unforeseen delays.

FDOT hired SICE as the contractor to complete this project for $4.5 million.

The Interstate 95 Nassau County ITS project involves installing traffic cameras and vehicle detection sensors on the roadway. ITS allows emergency agencies to utilize enhanced technology to better detect traffic slowdowns and incidents. This information can then be passed along to motorists through digital message boards installed on the interstate and through the FDOT 511 system.

The vehicle detection sensors will alert staff at regional traffic management centers of a slowdown or incident, and the cameras allow access to real-time video of the portion of the roadway in question. This information can then be displayed on the digital message boards and reported to 511, which provides motorists with additional methods of retrieving information – through phone, social media, or the 511 website.

The technology here is used for traffic monitoring purposes only. The cameras do not record and no footage is stored by FDOT.

Traffic Impacts

I-95 traffic impacts in Nassau County
June 15-21, 2019

Daytime lane closures from 8 a.m. to 5 p.m. Monday and Tuesday southbound near the Nassau County line and Georgia State line for Gateway sign and guardrail construction.

Daytime lane closures from Florida State Line to Georgia exit 22 (Horsestamp Church Road) for GDOT resurfacing project.

Daytime lane closures over Nassau River Bridge Monday and Tuesday from 9:30 a.m. to 3:30 p.m. for bridge work.

Project Photos

Project Documents

No documents at this time.
No Events at this time.

Project Details

Project Start:November 2017
Expected Completion:Spring 2019
Cost:$4.5 million
Project #:427475-1
RoadsInterstate 95, State Road 200, State Road A1A
CountiesDuval, Nassau
Cities

Contact

Samantha Rambeau
386-269-3602

Interstate 95 ITS Freeway Management Project

Overview

This is a 17-mile ITS (Intelligent Technology System) Freeway Management project along Interstate 95 from Airport Road in Duval County to the Florida-Georgia state line in Nassau County that incorporates a portion of A1A/State Road 200 just east and west of Interstate 95.

The project began in November 2017 with completion anticipated in spring 2019, depending on weather and unforeseen delays.

FDOT hired SICE as the contractor to complete this project for $4.5 million.

The Interstate 95 Nassau County ITS project involves installing traffic cameras and vehicle detection sensors on the roadway. ITS allows emergency agencies to utilize enhanced technology to better detect traffic slowdowns and incidents. This information can then be passed along to motorists through digital message boards installed on the interstate and through the FDOT 511 system.

The vehicle detection sensors will alert staff at regional traffic management centers of a slowdown or incident, and the cameras allow access to real-time video of the portion of the roadway in question. This information can then be displayed on the digital message boards and reported to 511, which provides motorists with additional methods of retrieving information – through phone, social media, or the 511 website.

The technology here is used for traffic monitoring purposes only. The cameras do not record and no footage is stored by FDOT.

Project Details

Project Start:November 2017
Expected Completion:Spring 2019
Cost:$4.5 million
Project #:427475-1
RoadsInterstate 95, State Road 200, State Road A1A
CountiesDuval, Nassau
Cities

Contact

Samantha Rambeau
386-269-3602

Traffic Impacts

I-95 traffic impacts in Nassau County
June 15-21, 2019

Daytime lane closures from 8 a.m. to 5 p.m. Monday and Tuesday southbound near the Nassau County line and Georgia State line for Gateway sign and guardrail construction.

Daytime lane closures from Florida State Line to Georgia exit 22 (Horsestamp Church Road) for GDOT resurfacing project.

Daytime lane closures over Nassau River Bridge Monday and Tuesday from 9:30 a.m. to 3:30 p.m. for bridge work.

Project Photos

 
Link to FDOT's Facebook page (opens new browser window) Link to FDOT's Twitter page (opens new browser window) Link to FDOT's YouTube page (opens new browser window) Link to FDOT's Wordpress page (opens new browser window) Link to FDOT's Multimedia page (opens new browser window) Link to FDOT's RSS page (opens new browser window)