Arlington Expressway (State Road 115) from Mathews Bridge to Southside Boulevard Resurfacing
Overview
The Arlington Expressway resurfacing project includes resurfacing of the expressway and service roads from the Mathews Bridge to Southside Boulevard, ADA and traffic signal upgrades and median improvements. The project also includes removal of the eastbound expressway ramp to Colcord Avenue, drainage work, sidewalk repairs and concrete work at Cesery Boulevard. In addition, the bridge over Red Bay Branch located on the south side service road east of the Arlington Road intersection will be rehabilitated. Superior Construction is the contractor for the $26 million project. Construction will begin in spring 2023 and be completed in summer 2024.
Traffic Impacts
Project Photos
Project mapProject map showing Red Bay BridgesColcord Avenue exit removalDecember 2023 Construction photosDecember 2023 Construction photosDecember 2023 Construction photosDecember 2023 Construction photosDecember 2023 Construction photos380397472485
Open House (Thursday, March 9, 2023)

A virtual and in-person construction open house will be held Thursday, March 9, 2023, from 4 – 6 p.m. at Arlington Congregational Church, 431 University Boulevard North, Jacksonville, FL 32221. FDOT staff and project representatives will be available to answer questions about the upcoming resurfacing project.

To register for the meeting, go to https://attendee.gotowebinar.com/register/5257763877826841692.

Participants who are unable to attend the webinar virtually or in-person may listen to the meeting by calling (562) 247-8422 Attendee code: 118-874-342. All participants, regardless of the platform they choose, will be able to view project documents and ask questions.

Project Details
Project Start:Spring 2023
Expected Completion:Fall 2024
Cost:$26 million
Project #:443310-1
RoadsState Road 115
CountiesDuval
CitiesJacksonville
Contact
Photo of Briana Ray-TurnerBriana Ray-Turner
904-360-5481
Arlington Expressway (State Road 115) from Mathews Bridge to Southside Boulevard Resurfacing
Overview
The Arlington Expressway resurfacing project includes resurfacing of the expressway and service roads from the Mathews Bridge to Southside Boulevard, ADA and traffic signal upgrades and median improvements. The project also includes removal of the eastbound expressway ramp to Colcord Avenue, drainage work, sidewalk repairs and concrete work at Cesery Boulevard. In addition, the bridge over Red Bay Branch located on the south side service road east of the Arlington Road intersection will be rehabilitated. Superior Construction is the contractor for the $26 million project. Construction will begin in spring 2023 and be completed in summer 2024.
Project Details
Project Start:Spring 2023
Expected Completion:Fall 2024
Cost:$26 million
Project #:443310-1
RoadsState Road 115
CountiesDuval
CitiesJacksonville
Contact
Photo of Briana Ray-TurnerBriana Ray-Turner
904-360-5481
Events
Open House (Thursday, March 9, 2023)

A virtual and in-person construction open house will be held Thursday, March 9, 2023, from 4 – 6 p.m. at Arlington Congregational Church, 431 University Boulevard North, Jacksonville, FL 32221. FDOT staff and project representatives will be available to answer questions about the upcoming resurfacing project.

To register for the meeting, go to https://attendee.gotowebinar.com/register/5257763877826841692.

Participants who are unable to attend the webinar virtually or in-person may listen to the meeting by calling (562) 247-8422 Attendee code: 118-874-342. All participants, regardless of the platform they choose, will be able to view project documents and ask questions.

Project Documents
Arlington Expressway Handout
Project Photos
Project mapProject map showing Red Bay BridgesColcord Avenue exit removalDecember 2023 Construction photosDecember 2023 Construction photosDecember 2023 Construction photosDecember 2023 Construction photosDecember 2023 Construction photos380397472485
 
Link to FDOT's Facebook page (opens new browser window) Link to FDOT's Twitter page (opens new browser window) Link to FDOT's YouTube page (opens new browser window) Link to FDOT's Wordpress page (opens new browser window) Link to FDOT's Multimedia page (opens new browser window) Link to FDOT's RSS page (opens new browser window)