U.S. 17 Governors Creek Bridge Sidewalk
Overview

This project involves sidewalk installation, milling and resurfacing, shoulder treatment, drainage improvements, curb and gutters, highway signing and other incidental construction on U.S. 17/State Road 15 at Governors Creek Bridge in Clay County. No lane closures on U.S. 17 will be permitted between 7 a.m. and 7 p.m. seven days a week.

Gosalia Concrete Constructors was selected as the primary contractor for this project.

Traffic Impacts
U.S. 17 traffic impacts
January 9-15, 2021

Nighttime lane closures at Governors Creek Bridge weeknights from 7 p.m. to 7 a.m. for bridge work.

Project Photos
No photos at this time.
Project Documents
No documents at this time.
No Events at this time.
Project Details
Project Start:July 2020
Expected Completion:Early 2021
Cost:$954,000
Project #:441406-1
RoadsU.S. 17
CountiesClay
CitiesGreen Cove Springs
Contact
Photo of Sara PleasantsSara Pleasants
386-269-3490
U.S. 17 Governors Creek Bridge Sidewalk
Overview

This project involves sidewalk installation, milling and resurfacing, shoulder treatment, drainage improvements, curb and gutters, highway signing and other incidental construction on U.S. 17/State Road 15 at Governors Creek Bridge in Clay County. No lane closures on U.S. 17 will be permitted between 7 a.m. and 7 p.m. seven days a week.

Gosalia Concrete Constructors was selected as the primary contractor for this project.

Project Details
Project Start:July 2020
Expected Completion:Early 2021
Cost:$954,000
Project #:441406-1
RoadsU.S. 17
CountiesClay
CitiesGreen Cove Springs
Contact
Photo of Sara PleasantsSara Pleasants
386-269-3490
Traffic Impacts
U.S. 17 traffic impacts
January 9-15, 2021

Nighttime lane closures at Governors Creek Bridge weeknights from 7 p.m. to 7 a.m. for bridge work.

 
Link to FDOT's Facebook page (opens new browser window) Link to FDOT's Twitter page (opens new browser window) Link to FDOT's YouTube page (opens new browser window) Link to FDOT's Wordpress page (opens new browser window) Link to FDOT's Multimedia page (opens new browser window) Link to FDOT's RSS page (opens new browser window)