State Road 200 landscaping projects
Overview

The Florida Department of Transportation of is preparing to begin landscaping improvements on State Road 200 in February 2023. The proposed landscaping improvements are organized into three different projects: State Road 200 from West of Still Quarters to West of Rubin Davis Lane (FIN# 4377291); State Road 200 from West of Rubin Davis Lane to East of County Road 107 (FIN# 4412901); State Road 200 from I-95 at State Road 200 Diverging Diamond Interchange to Still Quarters Road (FIN# 4412911)

Arazoza Brothers was selected to complete the project in February 2023 for a total cost of $6.1 million. State Road 200 from West of Still Quarters to West of Rubin Davis Lane is expected to cost $960,000. State Road 200 from West of Rubin Davis Lane to East of County Road 107 is expected to cost $2.9 million. State Road 200 from I-95 at State Road 200 Diverging Diamond Interchange to Still Quarters Road is expected to cost $2.23 million.

Traffic Impacts
State Road 200 traffic impacts
September 9-15, 2023
Nighttime lane closures Saturday through Thursday from 8 p.m. to 6 a.m. for work related to the landscaping project.
Project Photos
No photos at this time.
Project Documents
No documents at this time.
No Events at this time.
Project Details
Project Start:Early 2023
Expected Completion:Late 2024
Cost:$6.1 million
Project #:445341-1-52-01
RoadsState Road 200, State Road A1A
CountiesNassau
CitiesYulee
Contact
Photo of Samantha RambeauSamantha Rambeau
904-360-5484
State Road 200 landscaping projects
Overview

The Florida Department of Transportation of is preparing to begin landscaping improvements on State Road 200 in February 2023. The proposed landscaping improvements are organized into three different projects: State Road 200 from West of Still Quarters to West of Rubin Davis Lane (FIN# 4377291); State Road 200 from West of Rubin Davis Lane to East of County Road 107 (FIN# 4412901); State Road 200 from I-95 at State Road 200 Diverging Diamond Interchange to Still Quarters Road (FIN# 4412911)

Arazoza Brothers was selected to complete the project in February 2023 for a total cost of $6.1 million. State Road 200 from West of Still Quarters to West of Rubin Davis Lane is expected to cost $960,000. State Road 200 from West of Rubin Davis Lane to East of County Road 107 is expected to cost $2.9 million. State Road 200 from I-95 at State Road 200 Diverging Diamond Interchange to Still Quarters Road is expected to cost $2.23 million.

Project Details
Project Start:Early 2023
Expected Completion:Late 2024
Cost:$6.1 million
Project #:445341-1-52-01
RoadsState Road 200, State Road A1A
CountiesNassau
CitiesYulee
Contact
Photo of Samantha RambeauSamantha Rambeau
904-360-5484
Traffic Impacts
State Road 200 traffic impacts
September 9-15, 2023
Nighttime lane closures Saturday through Thursday from 8 p.m. to 6 a.m. for work related to the landscaping project.
 
Link to FDOT's Facebook page (opens new browser window) Link to FDOT's Twitter page (opens new browser window) Link to FDOT's YouTube page (opens new browser window) Link to FDOT's Wordpress page (opens new browser window) Link to FDOT's Multimedia page (opens new browser window) Link to FDOT's RSS page (opens new browser window)