Overview
The Florida Department of Transportation has started bridge reconstruction work on County Road 200A over Lofton Creek in Nassau County.
Temporary lane closures may be necessary throughout construction.
Superior Construction started construction on this $4.2 million dollar bridge replacement project in summer 2021 and is expected to complete it by summer 2022.
Traffic Impacts
Pages Dairy Road - CR 200A traffic impacts
June 27-July 1, 2022
Daytime lane closures Monday through Wednesday and Friday from 8:30 a.m. to 5:30 p.m. and daytime lane closures Thursday from 4 a.m. to 4 p.m. as part of the Lofton Creek Bridge project.
Project Photos
No photos at this time.
Project Documents
No documents at this time.
No Events at this time.