A $6.7 million project began in November 2019 and includes the demolition and replacement of the current C Street Bridge. The project is expected to be completed in early 2021, weather and unforeseen circumstances permitting. The new bridge will be raised three feet and consist of a 17-foot, one-way travel lane, dual 8-foot parking lanes, and dual 6-foot sidewalks.
During construction, a temporary bridge will be constructed to maintain access to the shops and restaurants on Dock Street.
Anderson Columbia Co., Inc., of Lake City, has been hired to complete the work for FDOT.