Halifax Paving, Inc. was selected to complete this $8.3 million project, which includes milling and resurfacing of the roadway, corridor improvements, base work, shoulder treatment, drainage improvements, curb and gutter work, lighting improvements, highway signing, guardrail installation, sidewalk work, pavement markings and other incidental construction.
Traffic will be maintained in accordance with FDOT design standards throughout the project. Motorists should expect lane closures from 8:30 a.m.to 5:30 p.m. Monday through Friday. No lane closures will be permitted from 6 a.m. to 8:30 a.m. Monday through Friday.