For additional information on the current situation, please visit the alerts page. FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Florida Department of
TRANSPORTATION
Safety, Innovation, Mobility, Attract, Retain & Train
Florida Department of
TRANSPORTATION
Safety, Innovation, Mobility, Attract, Retain & Train
First Coast Expressway – East of CR 2209 to East of CR 16A
Overview

This segment of the First Coast Expressway consists of a new four-lane limited-access toll facility from east of the County Road 16A to east of County Road 2209 in St. Johns County. De Moya Asphalt Joint Venture. was awarded the contract to construct this project, which includes milling and resurfacing, earthwork, subsoil excavation, base work, shoulder treatment, drainage improvements, curb and gutter, traffic signals, lighting, highway signing, guardrail, box culverts, bridges, MSE walls, sidewalks/bicycle path, intelligent transportation systems (ITS), tolling, and other incidental construction.

No lane closures will be permitted on County Road 2209 (St. Johns Parkway) from 7 to 9 a.m. No lane closures will be permitted on eastbound County Road 16A from 7 to 9 a.m. No lane closures will be permitted on westbound County Road 16A from 4 to 7 p.m.

Click here to view an interactive map of the project.

Traffic Impacts
Project Photos
MapFCE/St. Johns Parkway (CR 2209) interchange renderings (View 1)FCE/St. Johns Parkway (CR 2209) interchange renderings (View 2)
Hybrid Construction Open House (Tuesday, December 10, 2024)

A hybrid construction open house will be held from 4:30 to 6:30 p.m. Tuesday, Dec. 10, 2024. Attendees will have the opportunity to view exhibits, ask questions and speak with members of the project team.

In person: Renaissance World Golf Village, 500 South Legacy Trail, St. Augustine, FL 32092

Virtual: Register to participate at https://attendee.gotowebinar.com/register/5191291816963787096 using Webinar ID 346-130-707
Project Details
Project Start:November 2024
Expected Completion:2030
Cost:$242.6 million
Project #: 422938-8
RoadsState Road 23
CountiesSt. Johns
CitiesSt. Augustine
Contact
Photo of Sara PleasantsSara Pleasants
386-269-3490
First Coast Expressway – East of CR 2209 to East of CR 16A
Overview

This segment of the First Coast Expressway consists of a new four-lane limited-access toll facility from east of the County Road 16A to east of County Road 2209 in St. Johns County. De Moya Asphalt Joint Venture. was awarded the contract to construct this project, which includes milling and resurfacing, earthwork, subsoil excavation, base work, shoulder treatment, drainage improvements, curb and gutter, traffic signals, lighting, highway signing, guardrail, box culverts, bridges, MSE walls, sidewalks/bicycle path, intelligent transportation systems (ITS), tolling, and other incidental construction.

No lane closures will be permitted on County Road 2209 (St. Johns Parkway) from 7 to 9 a.m. No lane closures will be permitted on eastbound County Road 16A from 7 to 9 a.m. No lane closures will be permitted on westbound County Road 16A from 4 to 7 p.m.

Click here to view an interactive map of the project.

Project Details
Project Start:November 2024
Expected Completion:2030
Cost:$242.6 million
Project #: 422938-8
RoadsState Road 23
CountiesSt. Johns
CitiesSt. Augustine
Contact
Photo of Sara PleasantsSara Pleasants
386-269-3490
Events
Hybrid Construction Open House (Tuesday, December 10, 2024)

A hybrid construction open house will be held from 4:30 to 6:30 p.m. Tuesday, Dec. 10, 2024. Attendees will have the opportunity to view exhibits, ask questions and speak with members of the project team.

In person: Renaissance World Golf Village, 500 South Legacy Trail, St. Augustine, FL 32092

Virtual: Register to participate at https://attendee.gotowebinar.com/register/5191291816963787096 using Webinar ID 346-130-707
Project Photos
MapFCE/St. Johns Parkway (CR 2209) interchange renderings (View 1)FCE/St. Johns Parkway (CR 2209) interchange renderings (View 2)
 
Link to FDOT's Facebook page (opens new browser window) Link to FDOT's Twitter page (opens new browser window) Link to FDOT's YouTube page (opens new browser window) Link to FDOT's Wordpress page (opens new browser window) Link to FDOT's Multimedia page (opens new browser window) Link to FDOT's RSS page (opens new browser window)

Florida Department of Transportation

Consistent, Predictable, Repeatable