Work will consist of wire rope replacement, coating of structural steel, drainage work and steel plate rehabilitation. The work will require lane closures and detours during off-peak traffic hours. The contractor is Abhe & Svoboda. The contract is for 436 days.

Bridge Information ​​
 
Roads Affected:
Counties: Duval
Cities: Jacksonville
Project Overview
Project began: September 2016
Expected Completion: Fall 2017
Cost of Project: $4.3 million