For additional information on the current situation, please visit the alerts page. FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.


Northeast Florida Roads

Northeast Florida Roads / Search / Hart Bridge rehabilitation

Hart Bridge rehabilitation


Work will consist of wire rope replacement, coating of structural steel, drainage work and steel plate rehabilitation. The work will require lane closures and detours during off-peak traffic hours. The contractor is Abhe & Svoboda. The contract is for 436 days.

Bridge Information ​​
 
Roads Affected:
Counties: Duval
Cities: Jacksonville
Project Overview
Meeting Date: September 2016
Meeting Time: Fall 2017
Cost of Project: $4.3 million

Contact
Hampton Ray
386-269-3269
Hampton.Ray@atkinsglobal.com