For additional information on the current situation, please visit the alerts page. FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Florida Department of
TRANSPORTATION
Safety, Innovation, Mobility, Attract, Retain & Train
Florida Department of
TRANSPORTATION
Safety, Innovation, Mobility, Attract, Retain & Train
I-95 Resurfacing from Moncrief Creek to Edgewood Avenue West
Overview

Resurfacing and roadway improvements on approximately one-mile of I-95 from just south of the Norwood Avenue (State Road 115) northbound off-ramp north to Edgewood Avenue West (State Road 111) are scheduled to begin the week of April 13.

The project includes milling and repaving the roadway, the on- and off-ramps at the Norwood Avenue/Lem Turner Road interchange and the northbound off-ramp and southbound on-ramp at Edgewood Avenue West. In addition, the northbound Norwood Avenue off-ramp deceleration lane will be widened and extended approximately 600 feet.

Project safety improvements include the installation of a new signalized intersection on Lem Turner Road at the I-95 southbound on- and off-ramps. The new intersection will feature crosswalks and sidewalks, and deck lighting will be installed under the overpass.

Work along the project limits also includes shoulder treatments and repairs, drainage improvements, curb and gutter repairs, guardrail replacements where needed, new LED highway lighting and other incidental construction.

Contractors will work weekdays from approximately 7:30 a.m. to 4:30 p.m. and weeknights from approximately 6:30 p.m. to 6 a.m. Southbound and northbound single and occasional double lane closures will be scheduled throughout the duration of the project, but not during peak driving times or on holidays or special events. Ramp lane closures and detours will be scheduled during evening hours.

Construction activities are subject to change based on traffic volumes.

The $3.4 million contract was awarded to Duval Asphalt Products, Inc. It is expected to be completed in Spring 2021, weather and unforeseen circumstances permitting.

Traffic Impacts
I-95 traffic impacts
October 17-23, 2020

Nighttime lane closure from Edgewood Avenue to Moncrief Bridge Thursday from 6:30 p.m. to 6:30 a.m. for bridge work.

Lem Turner Road traffic impacts
October 17-23, 2020

Daytime lane closures at I-95 weekdays from 8 a.m. to 5 p.m. for traffic signal work.

Project Photos
95 at 115
Project Documents
No documents at this time.
No Events at this time.
Project Details
Project Start:April 2020
Expected Completion:Spring 2021
Cost:$3.4 million
Project #:4398001
RoadsState Road 111, State Road 115
CountiesDuval
CitiesJacksonville
Contact
Photo of Debbie DelgadoDebbie Delgado
904-476-7138
I-95 Resurfacing from Moncrief Creek to Edgewood Avenue West
Overview

Resurfacing and roadway improvements on approximately one-mile of I-95 from just south of the Norwood Avenue (State Road 115) northbound off-ramp north to Edgewood Avenue West (State Road 111) are scheduled to begin the week of April 13.

The project includes milling and repaving the roadway, the on- and off-ramps at the Norwood Avenue/Lem Turner Road interchange and the northbound off-ramp and southbound on-ramp at Edgewood Avenue West. In addition, the northbound Norwood Avenue off-ramp deceleration lane will be widened and extended approximately 600 feet.

Project safety improvements include the installation of a new signalized intersection on Lem Turner Road at the I-95 southbound on- and off-ramps. The new intersection will feature crosswalks and sidewalks, and deck lighting will be installed under the overpass.

Work along the project limits also includes shoulder treatments and repairs, drainage improvements, curb and gutter repairs, guardrail replacements where needed, new LED highway lighting and other incidental construction.

Contractors will work weekdays from approximately 7:30 a.m. to 4:30 p.m. and weeknights from approximately 6:30 p.m. to 6 a.m. Southbound and northbound single and occasional double lane closures will be scheduled throughout the duration of the project, but not during peak driving times or on holidays or special events. Ramp lane closures and detours will be scheduled during evening hours.

Construction activities are subject to change based on traffic volumes.

The $3.4 million contract was awarded to Duval Asphalt Products, Inc. It is expected to be completed in Spring 2021, weather and unforeseen circumstances permitting.

Project Details
Project Start:April 2020
Expected Completion:Spring 2021
Cost:$3.4 million
Project #:4398001
RoadsState Road 111, State Road 115
CountiesDuval
CitiesJacksonville
Contact
Photo of Debbie DelgadoDebbie Delgado
904-476-7138
Traffic Impacts
I-95 traffic impacts
October 17-23, 2020

Nighttime lane closure from Edgewood Avenue to Moncrief Bridge Thursday from 6:30 p.m. to 6:30 a.m. for bridge work.

Lem Turner Road traffic impacts
October 17-23, 2020

Daytime lane closures at I-95 weekdays from 8 a.m. to 5 p.m. for traffic signal work.

Project Photos
95 at 115
 
Link to FDOT's Facebook page (opens new browser window) Link to FDOT's Twitter page (opens new browser window) Link to FDOT's YouTube page (opens new browser window) Link to FDOT's Wordpress page (opens new browser window) Link to FDOT's Multimedia page (opens new browser window) Link to FDOT's RSS page (opens new browser window)

Florida Department of Transportation

Consistent, Predictable, Repeatable